FEATURED ARTICLE

 

METHODS AND PROCEDURES

by Samuel Y. Harris

with Rachel Royer

 

The term “methods and procedures” rises almost to the level of a code phrase for an array of specific and general issues associated with the construction industry.  The shortest and simplest introduction to the term and to its implications is to simply expand the words to a longer phrase, which begins to suggest those implications.  The methods and procedures at issue are those which are employed by contractors and builders in order to execute the design intentions presented by the design profession in the instruments of service, specifically the specifications and drawings for a given project.  Quite simply, the standard of the industry is that a design professional produces the design documents which are incorporated along with the contracts, bid forms, and other “front end” documents and which taken together are the instruments of service.

It is the responsibility of the contractor/builder to execute the project based on those instruments in manners and ways of her choosing as long as those ways and manners are reasonable and safe.  The presumption is that a practiced builder will elect methods most suitable from among equally valid approaches.  Because the builder is the party responsible for the safe and compliant execution of the design, it is legally and financially reasonable for her to choose from among the available viable methods and procedures to be employed at the job site.

This presumption within our industry has grown out of yet another presumption, which grossly and adversely affects our professions and our industry, namely, that the project involves a clear site and a new free-standing building.  This presumption and prejudice is implicit in standard AIA contracts, in professional educations of design professionals, in awards systems within the design professions, and within the legal precedents applicable to the governance of our industry.  As soon as the project involves an addition, a renovation, or an alteration, the weaknesses of these prejudices and presumptions begin to manifest.  When the project involves an existing, historic structure the manifest limitations of the prejudices and presumptions of the industry can and often are simply contrary to the interests of the parties.

As a general rule of property law and of the construction industry, the owner “brings the site”, meaning that the owner presents the site to both the design team and to the construction team.  Any flaws or detriments associated with the property are inherent in it and, therefore, also the property of the owner.  Such existing conditions include underground water, rock, graves and underground utilities, which may not be identified during due diligence conducted by the design professional.  This means that, unless negotiated otherwise, the owner bears the risks associated with the site.  If there is an uncharted underground stream below the surface and its discovery during construction adversely affects the builder, the owner bears the burden of the consequences.  While owners often resist this principle, they may keep in mind that the discovery of a significant gold deposit under the site also accrues to the owner, not the builder

Inasmuch as owners typically view the likelihood of hitting worthless rock or water as far greater than of hitting valuable ores, they may and often do want to shift the burden of risk to some other party; and, indeed, there is no principle of law prohibiting the redistribution of site related risks.  In the case of the discovery of below grade and untoward rock, the owner may instruct the design professional to specify that the excavation is "unclassified", which is a term of art meaning that the excavator agrees to create the required excavation regardless of what lies below the surface.  Needless to say, a prudent excavator will want to avoid unwarranted risks and may include as part of her bid sufficient amounts of money in order to conduct below grade explorations, or she may simply add enough money to overcome such risks.   Either way, the Owner has affected a reallocation of excavation risks.

The same principle applies to existing buildings: Unless otherwise reallocated, the risks associated with detriments and flaws of an existing structure are the property and responsibility of the owner. As with site conditions, the burden of discovery of such detriments does not automatically vest with the design professional and/or the construction team.  While such risks can be reallocated, if they are not specifically shifted and the designer or the builder is damaged or delayed during construction, the liability and burden of cost brought on by these conditions usually lies with the owner.

If a reasonable examination of existing buildings by the design professional prior to the start of construction uncovers no potentially detrimental conditions, the ultimate responsibility still lies with the owner if such conditions are discovered during construction. 

In a reasonable effort to reduce the risks of discovered conditions, owners often authorize and expect the design team to inspect and, in fact, to find the latent flaws of an existing building.  Certainly and important reason for conducting investigations and surveys is to determine the nature and extent of latent conditions which may affect construction feasibility.  Some owners assume that since the purpose of such efforts is to mitigate risk that they have effectively reallocated the risks as well.  This may or may not be the case.  If a practitioner understands that an essential element of an investigation is for the purpose of risk reassignment and agrees to accept the risk, then an owner may presume that she bears no further responsibility for the flaws of her building.  This is tempered by cases where the flaw was not "reasonably" apparent to the practitioner.  If, for example, the flaw lay buried inside a reinforced concrete column that exhibited no manifest distress, a reasonably diligent investigator is not normally held liable for the non-discovery of the flaw.  On the other hand, if a large crack is obviously increasing in length and width across a critical section of the same column and the investigator discounts the significance of such a crack, then she probably does so at her peril.

In instances involving modification of existing buildings, the reasons for an intervention may derive from any number of motives ranging from cosmetic to structural.  Regardless of the motive, the intervention in the building in any way is to some extent or other affected by the mere existence of the building as a physical object.  A carpenter cannot simply install a new floor joist, for example, without taking into account that the area is not free of obstructions and encumbrances to the removal of the existing joist and installation of the replacement.  The price and risk associated with such a replacement must and ordinarily takes into account the extraction, stabilization, and reinstallation sequence to affect the objective.  The development of the specific sequence of events resulting in the satisfactory replacement of the joist is typically reserved as the prerogative of the builder.  This is not unreasonable by virtue of the simple fact that the builder has to do the work, is responsible for compliance of the work with the design documents, and is historically responsible for methods and procedures pursuant to the work.

The rule becomes further complicated if the existing building is historic, either by specific designation or by common attribution of age.  The task of conserving historic fabric is added to the equation.  While it does not fall into the design professional’s normal scope of work to specify methods and procedures, failure to do so in the case of an historic structure leaves the door open for the builder to damage historic fabric.  This may not be intentional on the part of the builder, but unfamiliarity with such conditions may cause them to be unknowingly overlooked in the interest of completing the design intent in the least complicated, least costly manner. 

When building fabric begins to take on attributed historic value, the least expensive and least complicated approach to methods and procedures that will accomplish the design intent may not be appropriate.    In order to avoid unintentional damage that could be cause by the builder, a design professional experienced in working with historic structures must step in with a deliberate implementation plan.  Due to the added risks involved, agreements between design professionals and owners should more specifically outline the tasks of the job and how they are to be accomplished so the design professional is protected from added liability associated with assuming the role of determining the methods and procedures for a project.  

For example, simply calling for reinforcement of an historic structure with a steel I-Beam is not sufficient.  The builder could assume that the easiest way to get the I-Beam in is to knock a hole in the wall, which would result in a loss of fabric.  Instead, the design professional could specify that the beam be segmented and inserted through existing openings and reassembled with splice plates once in place.  By prescribing the method of installation, the design professional exercises his expertise in a specific area with which a general contractor may or may not be familiar.   If the owner is concerned with conservation of material, it may be inadvisable to surrender the selection of methods and procedures to a party who is, otherwise, fully entitled to employ the least expensive means available and who may not be professionally qualified to perceive the inherent disadvantages of a selected method.

The proposal to have the design professional stipulate methods and procedures rather than allowing the builder to do so causes a potential conflict with liability.  Currently, methods and procedures are left up to the builder and the liability for the efficacy of those methods and procedures flows to the builder. Reassigning the task of deciding methods and procedures to the design professional effectively removes that liability from the builder.  However, it is contrary to the standard language of AIA contracts and insurance policies for the design professional to assume the liability for methods and procedures.  The design professional is left in an awkward position with a difficult decision to make: Expose the building to the risk of damaged or lost historic fabric or expose himself to an uninsured professional risk.

S. Harris & Co. recently assumed this professional risk in the interest of conserving historic material.  The firm prescribed a step-by-step method to stabilize the Mensch Mill Barn in Alburtis, Pennsylvania.  This project was unusual and should not be viewed as a general recommendation.  Ordinarily, it is the practice of S. Harris & Co. to stabilize a structure in its existing form, rather than attempting to reverse the consequences of time.  However, in this particular case, the distortion of the structural members of the barn resulted in severe disengagement of joints.  The lightness and flexibility of the frame allowed for some degree of distortion reversal, which was determined to be appropriate, feasible and desirable.

If the drawings simply called for the building to be straightened to a certain degree, there would be a risk of fracturing the surviving joints.  Instead, the drawings called for a prescriptive procedure with Engineering supervision, allowing for the option to interrupt the process if required.  Existing conditions were documented on the first few pages of the drawing set and were followed by a page containing the Scope of Work.  The eleven steps in the Scope were then illustrated on the remaining pages in the drawing set.  Due to the delicate state of the structure, sequencing is very important in this procedure. 

Step One was to install shoring at all bents in the specified location.  Once shoring was in place, Step Two was to remove the upper scissor braces at all locations.

 

Step Three was to insert horizontal braces at all bents along the collector beam for added stability.  More support was added in Step Four, when diagonal knee braces were called out for installation at all bents.

 

With the additional support in place, the lower scissor braces were removed at all locations in Step Five.

 

The straightening process began in Step Six, with the installation of east-west tie rods at bents B, C, C’ and D.  This step called for a specific connection detail, shown below.

 

A similar connection detail was required for Step Seven, in which the installation of diagonal tie rods, at specified locations, was called for.

 

All turnbuckles on each tie rod were to be evenly and slowly tightened, ½ turn at a time in Step Eight.  This precise process was specified to continue under direction of the engineer until instructed by that engineer to stop.  Once the structure was pulled back into an acceptable position, Step Nine specified that it be kept in that position by installing bent steel plates to hold all horizontal members in position against the rafter plate.  Next, the installation of additional tie rods was called for in Step Ten for triangulation, providing lateral bracing at all columns. 

The final step, Step Eleven, was to remove all shoring and knee bracing and allow the stabilized and reinforced structure to stand.  

The process was as much an engineering issue as the finished product.  The prescription of specific methods and procedures in historic preservation should not be unusual.  To do otherwise is more professionally irresponsible than the consequence of venturing into a non-traditional area of professional responsibility in the construction field.

Construction history, liability and law hold that design professionals should not cross into the area of methods and procedures.  There is an existing conflict between contract law, insurance law and the realities of the associated risks of preservation.  There is no easy way to reconcile this conflict between the parties involved: the design professional, the builder, the legislature, the insurance industry and the owner.

The design professional is not covered by current contract or insurance language to certify to the owner that methods and procedures are up to construction standards.  By doing so, the design professional is effectively self-insuring, which could result in negligence on their part and increase risk for the owner.  Without the backing of insurance, the design professional probably does not have the money to back themselves, so the ultimately, according to the Rule of Agency, liability falls to the owner if there is added cost resulting in methods and procedures specified by the design professional.

Moving the liability of methods and procedures elsewhere puts the builder in a good position.  Compensation would be adjusted accordingly for the effort of execution of the methods and procedures prescribed by the design professional and the builder would be absolved of any liability if the alteration did not perform as expected.  The contract documents should acknowledge the intrusion to typical prerogative of the builder.  Such a reassignment of tasks would most likely not raise protest from builders.

To expect change at the legislative level for this issue is unrealistic.  Changes in insurance are possible, but not likely.  Design professionals could add coverage to existing policies to include specifying methods and procedures.  Along the same lines, a design professional could break out a separate fee and acquire additional compensation from the owner designated specifically for the purchase of an insurance policy for the job in order for the design professional to assume the risk.  However, recognition of involvement in design/build activities would increase premiums across the board despite its application to only a few practitioners.  To expect the general practitioner not involved in projects on existing or historic buildings to absorb this cost is unrealistic.

The process of elimination places the burden of liability on the owner, which is the most practical solution from a business standpoint.  This would require informed consent or that the professional explain the methods and procedures to the owner.  The design professional must ensure that the owner is prepared to absorb the ultimate risk for the methods and procedures required to accomplish the project that they request and it should be written into the contract between the two parties.  With informed consent, the owner is not forced to assume the risk associated with the project; the owner is given the option to cancel the project, rather than being surprised by discovered conditions later in the project.

Assigning the increased liability to the owner may result in increased animosity toward preservationists and a decrease in the number of preservation projects undertaken.  Owners hire design professionals because they do not want to assume the responsibility of having to know how to fix a problem about which they know nothing.  They bring in professionals to relieve their stress and provide a solution.  Even if a design professional explains the solution to the owner, it does not give the owner the expertise the professional possesses.  Owners may view it as undesirable to assume liability when they have called a professional in to give attention to existing buildings in order to avoid the risk associated with the existing condition to be repaired.  If the process and responsibilities are not carefully explained by the Design Professional, Owners may choose to circumvent the system altogether and go for the quick, easy fix, rather than increasing their own liability for preservation purposes. 

Still, placing the liability on the owner for existing or historic building projects makes the most legal sense, because the Owner “brings the site”.  The original site condition requires engagement in risky methods in order to accomplish the owner’s objective.  This is always latent in a property, as much with an existing building as with the more generally acknowledged uncharted utilities.

Preservation projects must be a cooperative effort.  Owners that are undertaking an effort to preserve their building with the use of a design professional generally are already willing to assume a more complicated and costly project.  The redistribution of liability as discussed above ensures that the project is completed in a way that protects the most historic fabric while accomplishing the design objective.  As more properties are becoming historic and more citizens are taking an interest in preservation, revamping an outdated system is necessary.

 

--S. Harris & Co. Comprehensive Project List--